SUBJECT: A REPORT ON THE IMPLEMENTATION PROGRESS OF THE SAN RAFAEL
BICYCLE/PEDESTRIAN MASTER PLAN 2011 UPDATE.
Staff recommends accepting the report and presentation.
In 1998, the San Rafael Bicycle and Pedestrian Advisory Committee (BPAC) was established with the
specific purpose of creating a Bicycle/Pedestrian Master Plan. The BPAC, along with City staff, initiated
preparation of the Bicycle/Pedestrian Master Plan in January of 1999. On February 4 th , 2002, the City
Council adopted the Bicycle/Pedestrian Master Plan and a corresponding negative declaration.
For several years, city staff, the BPAC and consultants worked together to update the Plan. On April 4,
2011 City council adopted the Bicycle/Pedestrian Master Plan 2011 Update and corresponding negative
declaration. The adoption of the Plan "establishes eligibility for five consecutive rBicycle Transportation
Account] funding cycles". Therefore, in order to remain eligible for Bicycle Transportation Account (BTA)
grants the Plan must be updated every five years. We are currently half way through this period.
Since the adoption of the Bicycle/Pedestrian Master Plan 2011 Update, the BPAC has continued to as
a minimum of two times per year with the specific intent of discussing and addressing bicycle and
pedestrian related issues located within the City of San Rafael and to review the progress of the Bike/Ped
Plan 2011 Update.
It has been a practice of the Public Works Department to incorporate bicycle and pedestrian
improvements in all projects including slurry seal, overlay, intersection improvements, etc.
The San Rafael Bicycle/Pedestrian Master Plan 2011 Update proposes a continuous bicycle and
pedestrian network for travel within San Rafael and connecting to surrounding communities. The plan
Ffle No.: �2 L-110 I
Counc*11 Mee in
CSIs posiifion. — GA typ&dw Lpe9zb-
,SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page. 2
also calls for numerous pedestrian improvements, additional bicycle parking, school safety commute
programs, maintenance programs, and educational programs.
The main goal of the 2011 Plan Update is to make bicycle and pedestrian travel an integral part of daily
life in San Rafael and to make San Rafael a model city for alternative transportation.
The Bicycle/Pedestrian Master Plan 2011 Update is a living document which includes the following
objectives:
E Complete the network of bicycle and pedestrian routes
a Maintain and improve the quality of the established routes
E Increase the amount of bicycle parking
0 Coordinate with other modes of transportation for improved bicycle access
E Increase education of alternative modes of transportation
Increase education through bicycle and pedestrian safety programs
.w"rior to adoption of the 2011 update, and since the adoption of the original Bicycle Pedestrian Iflaster
*1an in February of 2002, the following bicycle facilities were installed:
0 3.9 miles of bicycle/multi-use paths (Class 1)
0 3.5 miles of bicycle lanes (Class 11)
N over 22 miles of signed bicycle routes (Class 111)
Implementation
Public Works staff has been working diligently to secure construction funding, design and install the
proposed improvements listed in the Plan Update since its adoption in April of 2011. Proposed
improvements are broken into near, mid and long term categories. There are over ninety separate
bicycle and pedestrian related projects contained within the plan.
Near Term Priority Bicycle Facility Segments (2011 Update)
Projects listed in this category are proposed to be completed within 5 years of the adoption date of the
plan. The specific projects listed in this category can be found on page 59 of the plan. The followint
summarizes the progress on the near term bicycle facility project implementation:
Mid Term Priority Bicycle Facility Segments (2011 Update)
Projects listed in this category are proposed to be completed within 10 years of the adoption date of the
plan. The specific projects listed in this category can be found on page 60 of the plan. The following
summarizes the progress on the mid term bicycle facility project implementation. -
I
Facility Class•
Facility Class
11
(Bike Lanes)
I I
(Separated Path) (Bike Lane
(Bike Routes)
Proposed in Plan (miles)
2.66
7.o3
4.44
In Design (miles)
■II��®��*
,Il�ll��i *
0.36
0.00
Complete (miles)
���i i �, iii
i
i
design or complete
65.8%
two
63.3%
Mid Term Priority Bicycle Facility Segments (2011 Update)
Projects listed in this category are proposed to be completed within 10 years of the adoption date of the
plan. The specific projects listed in this category can be found on page 60 of the plan. The following
summarizes the progress on the mid term bicycle facility project implementation. -
I
1
se crated Path)
Facility Class
11
(Bike Lanes)
111
(Bike Route
Total
Pro osed in Plan (miles)_
2.66
7.o3
4.44
14.13
In Design (miles)
Complete (miles)
0.45
0.00
0.36
0.00
2.92
0.00
3.64
0.00
% in design or complete 1
16.9%
5.1%
65.8%
25.8% -------- J
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Pa2g: 3
Long Term Priority Bicy le Facility Segments (2011 ,Updatel
Projects listedin this category are proposed to be completed within 20 years of the adoption date of ft;
plan. The specific projects listed in this category can be found on page 63 of the plan. Work on the Long
Term Priority Bicycle Facility Segments has not yet begun.
Pedestrian Facilities (2011 Update)
Pedestrian improvements, including new sidewalk, curb ramps, pedestrian signal heads, bulb -outs, etc.
have been installed as part of many capital improvement projects. The following summarizes the progress
on the mid term bicycle facility project implementation:
Projects not in the Plan
Department of Public Works Staff are always looking for ways to improve the bicycle and pedestrian
facilities within City limits. As such, we sometimes identify locations in need of improvements that may
not have been specifically identified in the Bike/Ped Plan Update. Since the adoption of the Plan Update,
staff have identified and installed 0.31 miles of Class 11 bike lanes and 0.18 miles of Class III bike routes.
Grants
Bicycle and pedestrian improvements are costly to install. Over the past several years, local funding for
these types of improvements have been challenging to acquire. However, in order to continue to install
these types of improvements, Department of Public Works staff has been aggressively pursing grants that
can fund the types of improvements identified in the plan. Many of these grants require large amounts of
paperwork to apply. In addition, most grants are competitively awarded.
While grants for these types of projects are time consuming to apply for and difficult to acquire, •th
Department of Public Works utilizes gas tax and other local funding sources for small projects such a
Class 11 bike lane installations and Class III "sharrow" installations. Larger projects such as the bicycl
and pedestrian bridge proposed to cross the canal on Grand Avenue require large amounts of staff tim
to continually apply for grants and other funding sources in order to receive construction funding. I
Since the adoption of the Bicycle/Pedestrian Master Plan 2011 Update, Department of Public Works sta" r"
has applied for over $9.5 Million in grants. We have been awarded approximately 35% of the grantl
2pplied for. The following summarizes the projects and amount each grant was applied for- E
Project
Near Term
Project Category
Mid Term
=101IL!,N13-1 film
Approx.
Hours to
Apply
1 Proposed in Plan (projects
OBAG
213681178
11900,000
50
In Design (# of projects1°�-��)
Partially Complete (# of pr9ject
MAIN
Complete (# of projects)
% in design or complete
68.8%_
Projects not in the Plan
Department of Public Works Staff are always looking for ways to improve the bicycle and pedestrian
facilities within City limits. As such, we sometimes identify locations in need of improvements that may
not have been specifically identified in the Bike/Ped Plan Update. Since the adoption of the Plan Update,
staff have identified and installed 0.31 miles of Class 11 bike lanes and 0.18 miles of Class III bike routes.
Grants
Bicycle and pedestrian improvements are costly to install. Over the past several years, local funding for
these types of improvements have been challenging to acquire. However, in order to continue to install
these types of improvements, Department of Public Works staff has been aggressively pursing grants that
can fund the types of improvements identified in the plan. Many of these grants require large amounts of
paperwork to apply. In addition, most grants are competitively awarded.
While grants for these types of projects are time consuming to apply for and difficult to acquire, •th
Department of Public Works utilizes gas tax and other local funding sources for small projects such a
Class 11 bike lane installations and Class III "sharrow" installations. Larger projects such as the bicycl
and pedestrian bridge proposed to cross the canal on Grand Avenue require large amounts of staff tim
to continually apply for grants and other funding sources in order to receive construction funding. I
Since the adoption of the Bicycle/Pedestrian Master Plan 2011 Update, Department of Public Works sta" r"
has applied for over $9.5 Million in grants. We have been awarded approximately 35% of the grantl
2pplied for. The following summarizes the projects and amount each grant was applied for- E
Project
Grant
Amount
Requested
Amount
Received
Approx.
Hours to
Apply
Regional Transportation System
OBAG
213681178
11900,000
50
Enhancements
(install pedestrian safety improvements and
ADA access improvements within a 1/2mile
radius of the Bettini Transit Center and future
SMART rail station)
SRT
5001000
0
60
Grand Avenue Bridggj_
ABAG
2001000
2001000
45
(install a bridge on the east side of Grand
BTA
1,400,000
0
60
Avenue for the exclusive use of bicycles and
OBAG
116241526
0
50
pedestrians; modify 2 nd /Grand intersection for
increased ped safety)
HSIP
1,288,100
500,000 L_
100
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Pat1g.-_44
1- 35% 1
Legend:
OBAG One Bay Area Grant (Federally funded)
SR2T Safe Routes to Transit (Locally funded through Regional Measure 2)
ABAG Associate of Bay Area Governments, Bay Trails Grant
BTA = Bicycle Transportation Account
HSIP = Highway Safety Improvement Program (Federally funded)
CNTY = County of Marin Grant Program
SRTS = Safe Routes to School (Federally funded)
MTC = Metropolitan Transportation Commission
FISCAL IMPACT:
There is no fiscal impact associated with acceptance of this report and presentation. A large majority of
the improvements currently in design or completed are funded fully or partially by grants. Many of the
projects currently in design are in coordination with other agencies and entities such as Sonoma Marin
Area Rail Transit (SMART).
The majority of the fiscal impact for implementation of the Bicycle Pedestrian Master Plan 2011 Update is
staff time. Grant applications and coordination with other jurisdictions and entities (such as Sonoma
Marin Area Rail Transit (SMART)) take a significant amount of staff time. Staff time is paid for out of the
Department of Public Works operational budget.
• Accept the Report and Presentation
0 Reject the Report and Presentation
• Send back for additional study
ACTION REQUIRED:
a Accept the Report and Presentation
Amount
Amount
Approx.
Requested
Received
Hours to
Grant
Apply
-Project
Davidson Middle School
and ADA Access Improvements)
SRTS
565,000
565,000
40
-(Sidewalk
Bicycle Locker/Rack Installations
(Downtown and various City Owned Facility
Bicycle Parking Installations)
CNTY
12,169
12,150
25
PASS Grant
(Update traffic signal timings for minimum
and bicycle clearance times)
MTC
1927500
1927500
60
-pedestrian
Francisco Boulevard East Sidewalk Widening
HSIP
1,497,700
0
100
I TOTAL
9,657,173
3,369,669
590
1- 35% 1
Legend:
OBAG One Bay Area Grant (Federally funded)
SR2T Safe Routes to Transit (Locally funded through Regional Measure 2)
ABAG Associate of Bay Area Governments, Bay Trails Grant
BTA = Bicycle Transportation Account
HSIP = Highway Safety Improvement Program (Federally funded)
CNTY = County of Marin Grant Program
SRTS = Safe Routes to School (Federally funded)
MTC = Metropolitan Transportation Commission
FISCAL IMPACT:
There is no fiscal impact associated with acceptance of this report and presentation. A large majority of
the improvements currently in design or completed are funded fully or partially by grants. Many of the
projects currently in design are in coordination with other agencies and entities such as Sonoma Marin
Area Rail Transit (SMART).
The majority of the fiscal impact for implementation of the Bicycle Pedestrian Master Plan 2011 Update is
staff time. Grant applications and coordination with other jurisdictions and entities (such as Sonoma
Marin Area Rail Transit (SMART)) take a significant amount of staff time. Staff time is paid for out of the
Department of Public Works operational budget.
• Accept the Report and Presentation
0 Reject the Report and Presentation
• Send back for additional study
ACTION REQUIRED:
a Accept the Report and Presentation
CITY OF SAN RAFAEL
INSTRUCTIONS: USE THIS FORM WITH EACH SUBMITTAL OF A CONTRACT, AGREEMENT,
ORDINANCE OR RESOLUTION BEFORE APPROVAL BY COUNCIL / AGENCY.
SRRA / SRCC AGENDA ITEM NO. _6.a_
DATE OF MEETING: 1/21/14
FROM: NADER MANSOURIAN
• t•
IMPLEMENTATIONA REPORT ON THE ESAN RAFAEL BICYCLE/PEDESTRIAJ
UASTER PLAN 2011 UPDATE
00�
10"e� :"�— �Oze--7
Department Head (signature)
*** *** *** *** *** *** *** *** *** *** *** *** *** *** *** ***
(LOWER HALF OF FORM FOR APPROVALS ONLY)
APPROVED AS COUNCIL / AGENCY APPROVED AS TO FORM:
AGENDA ITEM:
File No.: 18.10.09