SUBJECT: Resolution Approving A Professional Services Agreement with Kimley-Horn
Consultants in an Amount Not to Exceed $270,000 for Work Related to the TAM Grant for the
Full or Partial Relocation of the San Rafael Transit Center Due to Impact of SMART Rail
Operations
RECOMMENDATION: Adopt Resolution.
BACKGROUND ON THE DOWNTOWN STATION AREA PLAN: The City of San Rafael
and our public agency partners at SMART, Golden Gate Bridge Highway and Transportation
District ("GGBHTD"), Marin Transit District and the Transportation Authority of Marin
("TAM"), collectively the Joint Project Team ("JPT") submitted a Station Area Plan grant
application to the Metropolitan Transportation Commission ("MTC") in 2009. MTC awarded
$488,000 for the Downtown Station Area Plan, including grant matching funds from the JPT in
the amount of $97,000. The City of San Rafael provided matching funds of $1,000, SMART
provided $41,000, GGBHTD provided $33,000, Marin Transit District provided $20,000, and
the TAM provided $2,000.
The City Council appointed the Citizens Advisory Committee on Economic Development and
Affordable Housing, formerly the Citizens' Advisory Committee on Redevelopment ("CAC")
which represents neighborhood, business, and property owners in San Rafael, including the
Downtown, to work with the community to develop the Downtown San Rafael Station Area Plan
and to advise the City Council on such Area Plan. Between July 2010 and March 2012, the
CAC worked on the Draft Station Area Plan at sixteen meetings; reviewed background data;
participated in two walking tours of the area; hosted two community outreach workshops, and a
series of presentations on the Draft Station Area Plan including presentations to the Boards of
TAM and Marin Transit, the Transportation Committee of the Golden Gate Bridge and
Transportation District, and the San Rafael Design Review Board and the San Rafael Planning
Commission. The CAC recommended Downtown San Rafael Station Area Plan was accepted by
the City Council on April 2, 2012. The City Council also directed staff to pursue implementation
of the Station Area Plan as infrastructure grant funding and staff resources became available.
FOR CITY CLERK ONLY
File No.: r'f � D
Council Meeting: L41LOLIO �5
Disposition: �t:�o� u tog) i�`►� 13
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
The Station Area Plan included some preliminary analysis on the potential full relocation of the
Bettini Transit Center. This initial work was included in the Downtown Station Area Plan to
address the negative impact on the transit center when the SMART train was extended to
Larkspur.
BACKGROUND ON THE BETTINI TRANSIT CENTER: The C. Paul Bettini Transit
Center (SRTC) is the major regional transit hub for Marin County. The Bettini Center is owned
by the Golden Gate Bridge Highway and Transportation District (GGBHTD), which provides
regional and inter county service operated by Golden Gate Transit. Other transportation services
operating at the SRTC include: intra -county local service by Marin Transit's contractors;
Sonoma County Transit; the Marin Airporter, which serves San Francisco Airport; the Sonoma
Airporter which serves Oakland Airport and Greyhound. A taxi stand operates inside the center.
These services all operate at the SRTC under Revocable License Agreements with GGBHTD.
The SRTC is composed of three separate parcels, APN 011-279-01 and 03 owned by GGBHTD.
APN 011-279-02 is owned by SMART. GGBHTD retained an easement over SMART's
property when it transferred ownership to SMART in 2006. The easement remains in effect until
SMART begins operating and when SMART extends service to Larkspur.
The SRTC accommodates approximately 575 busses per day on an average weekday with
service from public and private transit operators. Sonoma County Transit operates two trips/day
to and from Sonoma County, Marin Airporter operates 58 trips/day to and from San Francisco
Airport, Sonoma Airporter operates 30 trips/day to and from Oakland Airport and Greyhound
operates one trip/day in each direction linking San Rafael to San Francisco and the 101 corridor
cities in Northern California.
The SRTC current site is well situated for north -south trips with easy access to Highway 101 and
for east -west trips on the aerials of Second and Third Streets. The current location is adjacent to
roughly 197 free commuter parking spaces in Park and lZide lots under US 101 owned by Cal
Trans. Additional paid parking is available to commuters in the City's downtown garages
located within walking distance of the SRTC.
DISCUSSION: While SMART operations to Larkspur will be a benefit to the whole
community, it will have a negative impact on the operations at the SRTC as the train tracks will
be located through the center of SRTC. Negative impacts include the loss of the current two bus
bays at Platform C and the taxi parking -waiting area and the narrowing of the drive aisle width
used by the busses to navigating through the transit center. The SMART tracks will also require
fencing or other barriers that will eliminate the current pedestrian crossing through the transit
center, making the center less useable for patrons transferring between bus routes.
The negative impact on the transit center will require the full or partial relocation of the center
after SMART operates to Larkspur. The Station Area Plan included some initial analysis of the
space and operational requirements to meet the current and future needs of bus passengers but
further study is necessary.
The City, in conjunction with our partners at GGBDTD and Marin Transit District applied to the
TAM in December 2013 for a grant to do further analysis on the transit center relocation. TAM
awarded $288,320 including $33,330 in local matching funds for the transit center relocation
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 3
study. This was memorialized in a cooperative funding agreement between TAM and the City
which was approved by the City Council on December 1, 2014.
The City is the lead agency on this contract and the Economic Development Manager is the
project manager for the contract.
Staff prepared a request for qualifications for a consultant which was widely distributed and
advertised in the Marin Independent Journal. The TAM funds are Federal Funds administered
through the California Department of Transportation ("CALTRANS"). CALTRANS requires all
contracts to establish a Disadvantaged Business Enterprise ("DBE) goal. City staff worked with
TAM staff to establish a goal of 6% for this consulting contract. On February 24, 2015, a team
consisting of staff from the City of San Rafael, GGBHTD and Marin Transit District interviewed
three consulting firms for this study and Kimley Horn received the highest ranking. The Kimley
Horn cost proposal was for a total of $266,097.93 including work conducted by Strategic
Economics, Inc. a DBE firm whose work represents 15.62% of the total contract amount.
Kimley Horn's work will include the following:
• Operational analysis of the current transit operations
• Analysis of the land requirements for a new or partially relocated transit center and
related operational considerations
• An evaluation of the alternatives for a new or partially relocated transit center
• An evaluation of the real estate issues and alternatives for a new transit center or partial
relocation
• Analysis of reuse options for the existing Bettini Center
The proposed scope of work for the contract is included as Attachment A.
FISCAL IMPACT: On December 1, 2014, the City Council approved a funding agreement
with the Transportation Authority of Marin and authorized the appropriation of $288,320
including a local match of $33,330. The proposed scope of work from Kimley llorn is an
amount not to exceed $270,000.
The required match amount was acknowledged by our partners at Golden Gate Transit and Marin
Transit at the time the City of San Rafael applied for the TAM grant. In the event of any future
funding shortfalls for additional work not contemplated in the current approved scope of work,
we will work with our partners to address the issue.
OPTIONS:
1) Adopt the Resolution approving the contract with Kimley-Horn
2) Suggest changes to the proposed contract
3) Refuse to adopt the Resolution
ACTION REQUIRED: Adopt Resolution.
ATTACHMENTS:
A: Kimley Horn Scope of Services
ATTACH(`JIENT A
San Rafael Transit Center Relocation Study
Kimley-Horn Scope of Services
Task 1: Operational Analysis
Task 1.1: Obtain Background Information
Kimley-Horn will obtain the following information from the City of San Rafael, Marin Transit, and Golden
Gate Bridge Highway and Transportation District ("GGBHTD") (collectively, the Agencies):
- Existing bus schedules and routing
- Existing ridership by trip for all transit services operating at the existing transit center
- Existing on-time performance
- Existing and planned vehicle types
- Recent on -board survey and other analysis of trip origins and destinations for users of the transit
center
- Current planned and anticipated service modifications
- Recent vehicle, pedestrian, and bicycle counts for intersections in the vicinity of the transit center
- Property ownership, easements and agreements
- Existing and future level of service analysis in the vicinity of the transit center
- SMART Phase 1 and Phase 2 design plans and operating assumptions
- SMART station ridership projections
- Planned roadway, bicycle and pedestrian improvements in the vicinity of the station
- Downtown San Rafael Station Area Plan
- Planned development projects
- Any recent market analyses or other background information related to the real estate market
Task 1.2: Site Visit
Kimley-Horn will conduct one site visit with staff from the Agencies to review existing operations, parcel
ownership and relationship to SMART. Kimley-Horn will take minutes from the site walk and provide to the
Agencies for review.
Kimley-Horn will perform observations during the AM and PM peak commute periods to observe transit
center activity and estimate kiss -and -ride, taxi, shuttle and non -Agency activity levels.
Task 1.3: Transit Service Provider Interviews
Kimley-Horn will have one meeting each with Marin Transit and GGBHTD staff to discuss desired
amenities, and planned near-term and long-term operations at the San Rafael Transit Center. Meeting
minutes will be prepared after each of the interviews
Task 1.4: Route Analysis
Based on the information provided in Task 1.1, Kimley-Horn will prepare a brief fact sheet for each route
that currently serves the transit center. The fact sheet will contain the route alignment, frequency,
ridership, vehicle type, transfer characteristics (to the extent information is available from Task 1.1), and
identify any planned modifications to the route. A map will be prepared depicting bus volumes by general
approach direction.
Task 1.5: Baseline Circulation
Kimley-Horn will prepare graphics depicting existing facilities and circulation paths for bicycle, pedestrian
and auto movements into and out of the area in the vicinity of the transit center. A graphic will be
prepared displaying traffic volumes and peak period approach delays (assumed to be provided by the
City of San Rafael in Task 1.1) in the vicinity of the transit center. Similar graphics will be prepared for
planned facilities and future traffic forecasts (also provided by the City of San Rafael). This task does not
include any new traffic analysis.
Kimley-Horn will coordinate with City of San Rafael staff to understand traffic operations modifications
associated with the addition of SMART Phase 1 and Phase 2 (to the extent available). Changes to bus
circulation times associated with routes that cross the SMART tracks will be estimated and a range
calculated. It is assumed that limited information will be available regarding changes in auto traffic
patterns with the addition of the SMART crossings.
Task 1.6: Operational Analysis Report
Kimley-Horn will prepare a Draft Operational Analysis Report, summarizing the findings of this task,
including graphics and tables. The Draft Operational Analysis Report will be provided in PDF format to the
Agencies for review and comment. A meeting will be held to discuss Agency comments on the report and
develop consensus on any revisions to the Report. Kimley-Horn will prepare a Final Operations Analysis
Report and submit to the Agencies in PDF format.
Deliverable: Draft and Final Operational Analysis Report
Task 2: New Transit Center Land Requirements and Related Operational Considerations
Task 2.1: Identify Transit Center Amenities and Space Requirements
Based on the route analysis and service provider interviews performed in Task 1, Kimley-Horn will
estimate the total bay needs and stop location considerations for each of the routes serving the transit
center under existing and planned conditions. This will include bay sizes. Planned conditions will include
with SMART Phase 1 and with SMART Phase 2.
Based on the service provider interviews in Task 1 and the bay quantities, Kimley-Horn will develop a list
of amenities and accompanying land area requirements for the future transit center.
Task 2.2: Estimate Pedestrian Flows
Based on information collected in Task 1, Kimley-Horn will estimate pedestrian flows amongst the various
services planned for the transit center and to nearby land uses. This information will be summarized on a
cartoon graphic.
Task 2.3: Land Use Requirements Technical Memorandum
Kimley-Horn will prepare a draft technical memorandum in PDF format summarizing the findings of this
task. One round of non -conflicting, consolidated comments will be addressed and a final technical
memorandum will be prepared in PDF format.
Deliverable: Draft and Final Land Use Requirements Memorandum
Task 3: Alternatives Evaluation
Task 3.1: Identify Screening Criteria
Kimley-Horn will propose screening criteria to be utilized in the alternative evaluation. The screening
criteria will be summarized in a brief memorandum and provided for Agency comment.
Task 3.2: Site Identification
Kimley-Horn will identify potential sites and curb space that would be available for use in a transit center.
Sites will be identified based on acreage, access, and existing use. These sites will be identified on a
graphic. The graphic will be distributed to the Agencies for review and comment.
Task 3.3: Develop Long -Term Transit Center Configuration Alternatives
Kimley-Horn will develop up to nine alternatives of transit center configurations (including combinations of
on -street and off-street facilities) utilizing the potential sites identified in Task 3.1. Each alternative will be
shown on a conceptual graphic, not to scale, depicting approximate bus bay locations and configurations.
Bus, affiliated vehicle (i.e. kiss -and -ride, taxi and other vehicles serving the transit center), pedestrian,
and bicycle circulation graphics will be prepared for each concept depicting circulation with that concept.
A summary graphic will be prepared for each alternative highlighting conflict and control points for modal
interactions. For each alternative, a graphic will be prepared that provides a preliminary bay assignment
for each route serving the transit center.
Task 3.4: Bus Circulation Analysis
Using the Baseline Circulation analysis performed in Task 1.5, Kimley-Horn will estimate changes in
circulation times for each bus route serving the transit center from baseline conditions with each of the
proposed concepts. The changes in circulation times will be factored by bus frequency and summed to
quantify a change in circulation time from baseline conditions with each concept.
Task 3.5: Prepare Alternative Scenarios Report
Based on the screening criteria developed in Task 3.1, Kimley-Horn will prepare an evaluation of the
alternatives. The evaluation is anticipated to be primarily qualitative in nature. A matrix will be developed
comparing the performance of each of the alternatives.
Tasks 3.1 through 3.5 will be summarized in a technical memorandum. Kimley-Horn will provide a PDF
format draft of the memorandum for Agency review and comment. One round of non -conflicting Agency
comments will be addressed and a final technical memorandum prepared and provided to the Agencies in
PDF format.
Task 3.6: Alternatives Workshop
Kimley-Horn and the Agencies will hold a workshop to discuss the alternatives and the screening
evaluation. One preferred configuration will be identified, which may include one site or a combination of
sites. Kimley-Horn will prepare and distribute meeting minutes documenting the outcome of the
workshop.
Deliverables: Screening Criteria Memorandum, Sites for Consideration graphic, Draft and Final
Alternative Scenarios Report, Alternatives Workshop minutes
Task 4: Real Estate Evaluation
Task 4.1: Existing Conditions Assessment
Kimley-Horn will review the existing and potential access for the sites identified in Task 3.2, given the
existing transportation network and the alternatives developed in Task 3.3. Limitations to auto, pedestrian
and bicycle access for those sites will be identified on a graphic. Kimley-Horn will identify existing zoning
and planning requirements for those properties and display on a graphic.
Strategic Economics will conduct initial targeted analysis of market conditions in the study area as a
means to:
• Identify the most viable types of private development that might be considered as part of
subsequent tasks (e.g., office, residential, other uses); and
• Understand a range of likely land value s for sites considered as part of the alternatives analysis.
Task 4.2: Transit Center Integration
Kimley-Horn will evaluate the feasibility of integrating a transit center onto the identified sites given
existing and planned uses and the available transportation network, and identify the resulting effect on
existing and planned uses.
Strategic Economics will estimate the potential value that might be generated from up to three transit
center relocation scenarios that include a private development component. These scenarios might
include private development on the Bettini Transit Center site as well as other properties, with a focus on
uses determined to be most likely to be financially feasible and/or desired by the client.
Task 4.3: Real Estate Evaluation Assessment
This task will be summarized in a technical memorandum. Kimley-Horn will provide a PDF format draft of
the memorandum for Agency review and comment. One round of non -conflicting Agency comments will
be addressed and a final technical memorandum prepared and provided to the Agencies in PDF format.
Deliverable: Draft and Final Real Estate Evaluation Memorandum
Task 5: Preparation of the Conceptual Plan
Task 5.1: Develop Conceptual Plan
Based on the site selected in Task 3.7, Kimley-Horn will prepare a conceptual plan for the long-term
configuration of the transit center. The conceptual plan will be a plan view graphic, to scale, of the
proposed transit center and will include bus bay configuration, the location of amenities, access and
circulation roadways, and bicycle and pedestrian facilities. The plan will identify bus bay assignments and
the location of shuttle, taxi, and Greyhound and Airporter services. Concept plans will be drawn for up to
three alternative configurations of the same site(s). In addition to the conceptual plan, a graphic will be
prepared showing bicycle and pedestrian circulation within and to/from the transit center location(s).
Task 5.2: Conceptual Plan Workshop
A workshop will be held with the Agencies to discuss the conceptual plan. Kimley-Horn will prepare and
distribute meeting minutes that will contain agreed-upon revisions to the plan.
Task 5.3: Revisions to the Conceptual Plan
Kimley-Horn will implement the revisions to the plan agreed upon in Task 5.2 for one alternative.
Task 5.4: Cost Estimates
Kimley-Horn will prepare an opinion of probable cost for the construction of the conceptual plan and
amenities accompanying the proposed transit center based on similar recent projects in the Bay Area.
Deliverables: Conceptual Plan Workshop minutes, Conceptual Plan, Revised Conceptual Plan, Cost
Estimates
Task 6: Transition Strategies
Task 6.1: Transition Strategies
Based on existing operations (documented in Task 1) and the Conceptual Plan developed in Task 5,
Kimley-Horn will identify up to two alternative operating concepts for the following scenarios:
• SMART Phase 1 Operation
• SMART Phase 2 Construction
• Transit Center Construction (if affecting existing or interim transit center operations)
The concepts will be illustrated in not -to -scale graphics. Constraints to operations will be identified for
each alternative.
Task 6.2: Workshop on Transition Strategies
A workshop amongst the Agencies and Kimley-Horn will be held to discuss the alternative configurations
of the transit facilities during each of the transition scenarios. One preferred alternative for each scenario
will be identified. Kimley-Horn will prepare and distribute meeting minutes from the workshop.
Task 6.3: Refinement of Transition Configurations
Based on the preferred alternatives identified in Task 6.2, Kimley-Horn will prepare conceptual drawings.
Each transition scenario will have one plan view drawing of the bay locations, amenities and access
roadways. Cost estimates will be prepared for each of the preferred transition configurations.
Task 6.4: Transition Strategy Memorandum
A technical memorandum will be prepared summarizing the findings of this task. Also included in the
memorandum will be a discussion on operational considerations associated with the transition from one
scenario to the next and a graphical schedule summarizing the transition plan relative to triggering
events. Kimley-Horn will provide a PDF format draft of the memorandum for Agency review and comment.
One round of non -conflicting Agency comments will be addressed and a final technical memorandum
prepared and provided to the Agencies in PDF format.
Deliverable: Draft and Final Transition Strategy Memorandum
Task 7: Analysis of Reuse Options for Existing Bettini Center
Task 7.1: Land Plan
Kimley-Horn will develop up to three alternative land use scenarios for re -use of the existing Bettini
Transit Center. The land use scenarios will include potential densities by use, massing, and
access/egress points. Graphics will be prepared to illustrate the land use scenarios and access
configurations. A comparison matrix will be prepared to compare the three scenarios.
Task 7.2: Economic Evaluation
Building on information collected during Task 4, Strategic Economics will conduct pro forma analysis to
estimate the potential value that might be generated through sale or ground lease of the Bettini property.
This analysis will utilize the development scenarios created in Task 7.1, as well as assumptions about
construction costs, revenues from private development and other factors. The financial model may also
be used to test the sensitivity of development feasibility to key inputs such as on-site parking
requirements or other factors.
Task 7.3: Bettini Site Development Feasibility Memorandum
Kimley-Horn will prepare a draft technical memorandum in PDF format summarizing the findings of this
task. One round of non -conflicting, consolidated comments will be addressed and a final technical
memorandum will be prepared in PDF format.
Deliverable: Draft and Final Site Development Feasibility Memorandum
Task 8: Public Meetings and Outreach
Task 8.1: Team Meetings
Kimley-Horn will attend up to 8 monthly meetings amongst the Agencies to discuss project status and
coordination. Kimley-Horn will prepare and distribute meeting minutes.
Task 8.2: Board/Commission Meetings
Kimley-Horn will attend and assist in presenting the results of the study at up to two public
board/commission meetings.
Deliverable: Meeting minutes
Task 9: Draft and Final Report
Kimley-Horn will prepare a Draft Transit Center Relocation Study Report in PDF format, aggregating the
technical memorandums and deliverables developed in Tasks 1 through 7. Kimley-Horn will address one
round of non -conflicting comments from the Agencies to prepare a Final Transit Center Relocation Study
Report. Up to four hard copies and a PDF format copy of the Final Report will be provided.
Task 10: Project Management
Kimley-Horn will perform project management duties, including regular client coordination, monthly
invoicing, staff management, and work plan management.
RESOLUTION NO. 13913
RESOLUTION APPROVING A PROFESSIONAL SERVICES AGREEMENT
WITH KIMLEY-HORN CONSULTANTS IN AN AMOUNT NOT TO EXCEED
$270,000 FOR WORK RELATED TO THE TAM GRANT FOR THE FULL OR
PARTIAL RELOCATION OF THE SAN RAFAEL TRANSIT CENTER DUE TO
IMPACT OF SMART RAIL OPERATIONS
WHEREAS, in 2004, the City Council adopted General Plan 2020, which
included a number of policies related to the two planned Sonoma Marin Area Rail Transit
("SMART") rail stations in San Rafael, to be located in Downtown and at the Civic
Center; and
WHEREAS, staff pursued grant funding for planning the areas around these
stations consistent with General Plan 2020 policies and programs including: G -23b
Grants, NH -88a Transit Oriented Development, NH 88b Safe Walkways and Bikeways,
NH 36 Hetherton Office District, C17 Regional Transit Options and SMART, C18 Local
Transit Options and C20 Intermodal Transit Hubs; and
WHEREAS, in 2009, City staff and staff from other agencies met to prepare and
submit a Station Area Plan grant application to the Metropolitan Transportation
Commission ("MTC"). The public agency partners for the Downtown Station Area Plan
were the City of San Rafael, SMART, Golden Gate Bridge Highway and Transportation
District, Marin Transit District and the Transportation Authority of Marin ("TAM"),
collectively the Joint Project Team ("JPT"); and
WHEREAS, the JPT partner agencies provided grant matching funds in the
amount of $97,000. The City of San Rafael provided matching funds of $1,000, SMART
provided $41,000, Golden Gate Bridge Highway and Transportation District provided
$33,000, Marin Transit District provided $20,000, and the Transportation Authority of
Marin provided $2,000; and
WHEREAS, on May 3, 2010, the City Council authorized the City Manager to
Accept and Expend a Grant in the Amount of $528,000 from the Metropolitan
Transportation Commission for Station Area Plans for the Downtown and Civic Center
San Rafael Stations, of which a total of $488,000 was for the Downtown Station Area
Plan; and
WHEREAS, the City Council appointed the Citizens Advisory Committee on
Economic Development and Affordable Housing, formerly the Citizens' Advisory
Committee on Redevelopment ("CAC") which represents neighborhood, business, and
property owners in San Rafael, including the Downtown, to work with the community to
develop the Downtown San Rafael Station Area Plan and to advise the City Council on
such Area Plan; and
WHEREAS, between July 2010 and March 2012, the CAC worked on the Draft
Station Area Plan at sixteen meetings; reviewed background data; participated in two
walking tours of the area; hosted two community outreach workshops, and a series of
presentations on the Draft Station Area Plan including presentations to the Boards of
TAM and Marin Transit, the Transportation Committee of the Golden Gate Bridge and
Transportation District, and the San Rafael Design Review Board and the San Rafael
Planning Commission; and
WHEREAS, on April 2, 2012, the CAC presented its recommended Downtown
San Rafael Station Area Plan to the City Council, and the City Council accepted the Plan;
and
WHEREAS, on April 2, 2012 the City Council of the City of San Rafael also
directed staff to pursue implementation of the Station Area Plan as infrastructure grant
funding and staff resources became available; and
WHEREAS, in December 2013, the City of San Rafael in conjunction with the
Golden Gate Bridge and Highway District, the owner of the Bettini Transit Center, and
Marin Transit applied to TAM for a Priority Development Area ("PDA") grant to study
options for an integrated transit center in Downtown San Rafael. This study is necessary
due to negative impact on the existing Bettini Center from the future SMART extension
to Larkspur; and
WHEREAS, in December 2013, the City of San Rafael also applied to TAM for
a Priority Development Area ("PDA") grant to study parking and way finding in and
around the Downtown SMART Station; and
WHEREAS, TAM approved funds in the amount of $288,320 including a
required "local match" in the amount of $33,330 for further studies related to the
relocation of the transit center and $251,573 including a $29,082 local match for the
parking and way finding study.
WHEREAS, there are sufficient funds in the General Fund to support the
$33,330 required match for the transit center relocation study, and there are sufficient
funds in the Parking Fund to support the $29,082 required match for the parking study;
WHEREAS, on December 1, 2014 the San Rafael City Council accepted a grant
from TAM pursuant to cooperative funding agreement No. 2014-019 between the City of
San Rafael and TAM for the two grants;
WHEREAS, the City Council's action on December 1, 2014 to accept the two
grants from TAM pursuant to cooperative funding agreement No. 2014-019, also
approved the appropriation of $33,330 from the General Fund for the required local
match for this contract; and